Network Installation Cost Per Site
in 2026 — real ranges by site type.

Most vendors will not put a per-site number in writing until you sign something. This page does. Here are 2026 per-site installation ranges for retail, restaurant, office, clinic, and warehouse sites — from a contractor that has deployed 5,000+ sites across 48 states since 1996.

1996
Pricing site installs since
500+
Multi-site deployments
5,000+
Sites installed
48
States priced

In 2026, network installation costs $7,500-$16,500 per site for small retail or QSR locations, $18,000-$48,000 for large-format retail, $12,000-$32,000 for a restaurant's full technology stack, $9,500-$22,000 for a branch office or bank branch, $14,000-$34,000 for a medical clinic, and $35,000-$120,000 for a warehouse or distribution center. Standard offices run $250-$450 per user. These ranges cover install labor and install materials on 25+ site programs; network hardware is excluded. Expect ±30% variance for site conditions, and multi-site programs run 15-30% below single-site pricing at 25 or more sites.

SRS Networks is a nationwide enterprise infrastructure deployment company headquartered in Salinas, California, deploying network installations for multi-site organizations across all 48 contiguous US states since 1996. The ranges on this page come from our field data — not industry averages — so use them to build budgets and to pressure-test vendor quotes that look too low or too high.

What does network installation cost per site in 2026?

Per-site ranges by archetype. Install labor plus install materials; network hardware excluded unless stated. Ranges assume 25+ site programs.

Site archetypeTypical scope2026 per-site range
Small retail / QSR (2,500-5,000 sq ft)8-16 drops, 2-4 APs$7,500-$16,500
Large-format retail (15,000-60,000 sq ft)24-60 drops, 8-20 APs$18,000-$48,000
Restaurant full tech stackPOS + KDS + menu boards + drive-thru + WiFi + cameras$12,000-$32,000
Branch office / bank branch (2,000-6,000 sq ft)12-24 drops$9,500-$22,000
Medical clinic (3,000-10,000 sq ft)20-40 drops$14,000-$34,000
Warehouse / distribution center (50,000-300,000 sq ft)High-density WiFi + IDFs$35,000-$120,000
Standard officePer-user basis$250-$450 per user

2026 national planning ranges from SRS Networks field data across 500+ multi-site deployments. ±30% variance for site conditions, region, and scope.

What is in scope for each site type?

Same unit costs, different unit counts. Here is what each archetype actually includes — drops, APs, cameras, and terminals.

$7,500-$16,500

Small retail / QSR

2,500-5,000 sq ft · 8-16 drops · 2-4 APs

Cat6 drops to POS lanes, back office, and pickup screens, plus AP mounting and provisioning and a clean backboard or wall-mount rack. Adding a typical retail camera package of 8-16 cameras runs another $6,000-$16,000 installed.

$18,000-$48,000

Large-format retail

15,000-60,000 sq ft · 24-60 drops · 8-20 APs

Sales floor, stockroom, and receiving coverage push both drop counts and AP counts up. Longer home runs and lift work move sites toward the top of the range.

$12,000-$32,000

Restaurant full tech stack

POS + KDS + menu boards + drive-thru + WiFi + cameras

The densest small-footprint archetype. POS installs run $350-$850 per terminal, and a typical QSR site with 3-6 terminals lands at $2,500-$7,500 for POS work alone before kitchen display, menu boards, and drive-thru cabling.

$9,500-$22,000

Branch office / bank branch

2,000-6,000 sq ft · 12-24 drops

Teller lines, platform desks, and ATM/ITM connections. Security requirements — escorted access, after-hours windows — are the usual reason a branch lands above the midpoint.

$14,000-$34,000

Medical clinic

3,000-10,000 sq ft · 20-40 drops

Exam rooms, nurse stations, and imaging pull drop counts higher than square footage suggests. Occupied-space work and infection-control protocols add labor hours.

$35,000-$120,000

Warehouse / distribution center

50,000-300,000 sq ft · high-density WiFi + IDFs

The number is driven by WiFi density and backbone, not drop count. AP installs run $450-$900 each at height, and a fiber backbone from the MDF to 2-4 IDFs runs $8,000-$25,000 per building.

$250-$450 per user

Standard office

Per-user basis · cabling, switching, WiFi, rack

Offices price cleanest per user. Alternate framing: $1.50-$4.50 per sq ft for structured cabling only, or $3.00-$8.00 per sq ft for full network infrastructure. Full office math is on the office cost page below.

Unit rates behind the per-site numbers

Every per-site range above decomposes into these 2026 unit rates. If a vendor quote cannot be broken down this way, ask why.

Unit2026 installed range
Cat6 copper drop, installed and certified$175-$295
Cat6A copper drop, installed and certified$220-$390
WiFi AP install (mount + provision + one Cat6A drop)$450-$900 per AP
POS install (per terminal/lane, hardware excluded)$350-$850
IP camera, installed (mount + Cat6 drop + aim + VMS)$450-$1,100
Fiber building backbone (MDF to 2-4 IDFs, 12-strand OM4)$8,000-$25,000

2026 national planning ranges from SRS Networks field data across 500+ multi-site deployments. ±30% variance for site conditions, region, and scope.

What moves the per-site number up or down?

Six factors explain almost every quote that lands outside the table above.

Region & wage class

Tier-1 metros (NYC, SF, Boston, Chicago) run 25-40% above national ranges. Prevailing-wage scopes add another 30-50%.

Schedule & access

After-hours and overnight work adds 25-50% (1.25x-1.5x labor). Rush or emergency dispatch adds 50-100%.

Scope density

Drops, APs, cameras, and terminals per site are the core unit counts. A 40-drop clinic and a 12-drop branch are different jobs even at the same square footage.

Staging vs drop-ship

Without pre-staging, roughly 1 in 6 site visits hits missing, wrong, or damaged gear. Staged freight runs 3-6% of hardware value and protects the schedule.

Program scale

Multi-site programs at 25+ sites run 15-30% below single-site pricing because mobilization, staging, and management amortize across sites.

Site conditions

Ceiling type, pathway, riser access, and occupied-space constraints drive the ±30% variance band. Surveys ($150-$400 remote, $450-$1,200 on-site) tighten it.

How does per-site cost change with program scale?

The single most important pricing fact in this guide: the same site costs less inside a program than alone.

25 sites

The economic floor

Roughly 25 sites is where a national deployment partner starts beating local contractors — multi-site pricing runs 15-30% below single-site rates. Below that floor, per-site coordination overhead eats the margin, and SRS tells buyers to hire a local shop.

100 sites

Program pricing

At 100 sites the rate card is locked by archetype, gear pre-stages at West and East Coast facilities, and waves sequence by region. Per-site cost stabilizes because surprises get engineered out, not priced in.

500+ sites

National MSA rates

At 500+ sites, pricing moves to a national MSA rate structure — one rate card across all 48 contiguous states, so site 400 prices the same way site 4 did. This is how SRS prices national accounts.

Volume tierEffect on price
200+ drops on a single site5-15% below list
1,000+ drops on a single site10-20% below list
Multi-site program at 25+ sites15-30% below single-site pricing

2026 national planning ranges from SRS Networks field data across 500+ multi-site deployments. ±30% variance for site conditions, region, and scope.

How SRS prices per-site network installation

The most consistent request we see across the 200+ enterprise RFPs SRS answers each year is transparent per-site pricing. So that is how we price: a per-site fixed rate card by archetype — one number per site type, locked before the first wave, honored across all 48 contiguous states. Unit-rate schedules cover variable scopes, and time-and-materials is reserved for discovery and remediation work only.

Two honest caveats. First, below roughly 25 sites, hire a local shop — under the national-rollout economic floor, per-site coordination overhead eats the margin and a good regional contractor will beat our price. Second, the ±30% variance band is real: site surveys ($150-$400 remote, $450-$1,200 on-site) are how you shrink it before the rate card locks, not after.

Datacom products purchased through SRS carry a 5-year bumper-to-bumper SRS warranty, and gear pre-stages at our West and East Coast staging facilities — which is how we avoid the 1-in-6 drop-ship failure rate and target 98%+ first-visit completion. Field execution data lives on our field deployment benchmarks page.

Per-Site Cost FAQs

The questions multi-site buyers ask before locking a rate card.

In 2026, network installation runs $7,500-$16,500 per site for small retail/QSR, $18,000-$48,000 for large-format retail, $12,000-$32,000 for a restaurant's full tech stack, $9,500-$22,000 for a branch office, $14,000-$34,000 for a medical clinic, and $35,000-$120,000 for a warehouse or distribution center. Standard offices run $250-$450 per user. Ranges cover install labor and materials on 25+ site programs, with ±30% site-condition variance; network hardware is excluded.