1. Freeze the acceptance basis
The acceptance record begins with the contract, not the tester. Capture the exact topology and performance basis before results arrive.
Project documents
List the approved drawings, specifications, addenda, requests for information, change orders, and manufacturer requirements that govern the installed work. Record the revision used in the field.
Link model
State whether each population is a permanent link, channel, modular plug terminated link, backbone segment, or another expressly defined topology. The adapter and test limit must agree with that model.
Acceptance owner
Name who can approve exceptions, witness testing, receive the closeout folder, and sign the final acceptance. Do not leave approval distributed across emails with no accountable decision maker.
Pass rule
Define whether marginal results, informational flags, field re-certification, or manufacturer-specific warranty limits require review. The project specification controls; the tester's green indicator is evidence, not the entire contract.