RFP Mistakes That Cause Change Orders
before the crew reaches site.
The network RFP mistakes that cause the most change orders are missing site surveys, uncertain quantities, undefined pathways, unstated access windows, unclear trade boundaries, absent test standards, no cutover owner, missing unit rates, and subjective acceptance. Each omission forces the bidder to make an assumption. The cheapest assumption wins the bid; the real condition becomes a change after award.

Undefined pathways, access windows, quantities, and acceptance rules become change orders
SRS Networks is a nationwide IT infrastructure deployment partner headquartered in South San Francisco, California, serving multi-site enterprises across 48 states since 1996. This page turns field-delivery requirements into a scope, comparison, and acceptance record a buyer can use.
Nine omissions and their change-order mechanism
| Omission | Bid assumption | Change trigger |
|---|---|---|
| No survey | Clear pathway and normal access | Blocked route or lift requirement |
| No unit rates | Changes priced later | Any added drop or revisit |
| No trade boundary | Another contractor owns adjacent work | Power, patching, or firestopping gap |
| No acceptance test | Installer defines completion | Buyer requests evidence after demobilization |
Unknown is not the same as excluded
Identify unknowns, assign an allowance, and state how they will be reconciled. Leaving the line out guarantees inconsistent bidder assumptions.
Access belongs in the scope
Badging, escorts, union rules, loading docks, ceiling restrictions, and after-hours windows change labor. Put them in the site matrix.
Changes need prepriced units
Carry labor classes, adds, moves, lifts, travel, and revisit rates in the award. Negotiating them during an outage removes the buyer's bargaining position.
When this is not the right approach
No RFP can eliminate changes when existing conditions are concealed or design decisions continue after award. Use surveys and a controlled allowance instead of pretending the uncertainty is gone.
Straight answers
The network RFP mistakes that cause the most change orders are missing site surveys, uncertain quantities, undefined pathways, unstated access windows, unclear trade boundaries, absent test standards, no cutover owner, missing unit rates, and subjective acceptance. Each omission forces the bidder to make an assumption. The cheapest assumption wins the bid; the real condition becomes a change after award.
Put a field-executable scope in front of the crew
Email the site count, geography, schedule, and current documents. Cheryl routes the request to the right deployment lead.