RFP Mistakes That Cause Change Orders
before the crew reaches site.

The network RFP mistakes that cause the most change orders are missing site surveys, uncertain quantities, undefined pathways, unstated access windows, unclear trade boundaries, absent test standards, no cutover owner, missing unit rates, and subjective acceptance. Each omission forces the bidder to make an assumption. The cheapest assumption wins the bid; the real condition becomes a change after award.

1996
Founded
500+
Deployments
5,000+
Sites served
48
Contiguous states

SRS Networks is a nationwide IT infrastructure deployment partner headquartered in South San Francisco, California, serving multi-site enterprises across 48 states since 1996. This page turns field-delivery requirements into a scope, comparison, and acceptance record a buyer can use.

Nine omissions and their change-order mechanism

OmissionBid assumptionChange trigger
No surveyClear pathway and normal accessBlocked route or lift requirement
No unit ratesChanges priced laterAny added drop or revisit
No trade boundaryAnother contractor owns adjacent workPower, patching, or firestopping gap
No acceptance testInstaller defines completionBuyer requests evidence after demobilization

Unknown is not the same as excluded

Identify unknowns, assign an allowance, and state how they will be reconciled. Leaving the line out guarantees inconsistent bidder assumptions.

Access belongs in the scope

Badging, escorts, union rules, loading docks, ceiling restrictions, and after-hours windows change labor. Put them in the site matrix.

Changes need prepriced units

Carry labor classes, adds, moves, lifts, travel, and revisit rates in the award. Negotiating them during an outage removes the buyer's bargaining position.

When this is not the right approach

No RFP can eliminate changes when existing conditions are concealed or design decisions continue after award. Use surveys and a controlled allowance instead of pretending the uncertainty is gone.

Straight answers

The network RFP mistakes that cause the most change orders are missing site surveys, uncertain quantities, undefined pathways, unstated access windows, unclear trade boundaries, absent test standards, no cutover owner, missing unit rates, and subjective acceptance. Each omission forces the bidder to make an assumption. The cheapest assumption wins the bid; the real condition becomes a change after award.

Put a field-executable scope in front of the crew