How to Write an IT Project RFQ
when the scope is ready for price.
Write an IT project RFQ after the technical approach and quantities are fixed. Give every bidder the same site matrix, bill of quantities, labor units, material specifications, assumptions, alternates, schedule, acceptance criteria, quote-validity period, and commercial response form. If you are still asking vendors what to build, you need an RFP, not an RFQ.

Use an RFQ after the design is settled and vendors can price the same scope
SRS Networks is a nationwide IT infrastructure deployment partner headquartered in South San Francisco, California, serving multi-site enterprises across 48 states since 1996. This page turns field-delivery requirements into a scope, comparison, and acceptance record a buyer can use.
RFQ writing sequence
| Step | Decision | Output |
|---|---|---|
| 1 | Confirm design and quantities | Issued bill of quantities |
| 2 | Lock assumptions and alternates | Common pricing basis |
| 3 | Define schedule and acceptance | Executable delivery requirement |
| 4 | Issue one response form | Comparable vendor totals |
Use one pricing workbook
Protect formulas and define required cells. Vendors may attach narrative, but the controlling commercial response should be one normalized sheet.
State what can change
Name acceptable equals, substitution approval, quantity reconciliation, tax treatment, freight, and escalation after quote expiry.
Keep evaluation narrow
An RFQ is a commercial competition among already qualified vendors. Score compliance, schedule, exceptions, terms, and price without recreating a full RFP.
When this is not the right approach
Do not use an RFQ to obtain unpaid design from bidders. When architecture, product selection, or deployment method is unresolved, issue an RFP or buy a design phase.
Straight answers
Write an IT project RFQ after the technical approach and quantities are fixed. Give every bidder the same site matrix, bill of quantities, labor units, material specifications, assumptions, alternates, schedule, acceptance criteria, quote-validity period, and commercial response form. If you are still asking vendors what to build, you need an RFP, not an RFQ.